A task should start only when everything it needs is on site: the parts, the components and the consumables. That is a full kit. When a single part is missing, the crew waits, the task slips, and the delay runs down the project. Exepron Procurement connects the project plan to purchasing, so every task’s materials are ordered in time and every delay is visible before it hurts.
Watch: Setting Up Materials and Task Full Kits in Exepron
This tutorial follows one house build from the material catalog to the day the last part arrives. It has chapters, so you can jump to the part you need.
Setting Up Materials and Task Full Kits in Exepron (13 minutes)
- 0:00 Introduction
- 0:58 Access and settings
- 2:04 Import vendors and materials
- 3:53 Categorize the resource types
- 5:26 The materials list (bill of materials)
- 6:57 Put the requirement on a task
- 8:17 Order the materials
- 9:46 Receive deliveries
- 10:54 When requirements change
- 12:11 Reports and cost
- 13:03 Recap
Two products, one plan
Exepron, our AI-powered project portfolio management solution, plans and schedules the work. Exepron Procurement, an app in the Exepron App Store, is where buyers order, track and receive the materials. Both use the same account and the same sign-in, and every change in one shows up in the other straight away. The project manager says what each task needs; procurement makes sure it arrives.
How the procurement mechanism works
1. One material catalog and your vendors
The Material Catalog is the single list of every part the account buys, shared by all projects. Import an existing list from Excel: Exepron Procurement finds the header row, shows a preview of new and matching items, and saves nothing until you confirm. After that, the catalog edits like a spreadsheet: type in a cell, paste rows from Excel, copy and paste with the right-click menu.
For each vendor you record what it supplies: its own part number, the price per unit and the lead time. The same vendor can deliver one item in six days and another in thirty-five, and you mark the vendor you normally buy from as preferred.
2. Materials are resource types, but not capacity
In Exepron, materials are resource types, like skills, equipment and facilities. The difference is that a generator kit is bought, not scheduled. Resource categories tell Exepron how each resource type behaves: procured through Exepron Procurement, excluded from leveling and loading, or capacity-based. Materials and consumables are procured and left out of leveling, so the schedule keeps leveling only the resource types that really have capacity.
3. A materials list, built once
Each procured resource type has a materials list (a bill of materials): every part needed for one unit of it, grouped into assemblies such as Electrical or Framing. Build it by hand or import a long list from Excel. Quantities are per unit, so when a task needs two kits, every quantity doubles automatically.
4. The requirement on the task
The project manager assigns the material resource type to a task with the number of units. The task’s Full Kit Materials List then shows each part, the quantity needed and the date it is needed by, which is the task’s planned start. One-off parts can be added to a single task. Every planned task with materials creates demand in Exepron Procurement, with no copying and no spreadsheets in between.
5. Order, with the delay in plain sight
Orders lists every line the projects need, filtered by project, task or status: to order, late or at risk. Choose the vendor, and its lead time and price fill in. Exepron Procurement works out the expected delivery and warns when it falls after the need-by date. The Buffer impact column shows what a late part would cost the project: how much of the feeding or project buffer the delay would use, and when the project end date itself is at risk.
6. Receive, and everyone sees it
Deliveries are recorded with the date, the quantity and the delivery note, partial deliveries included. The project manager sees the progress on the task at once, and late parts are flagged everywhere the task appears: the task header, the task list, the Planning Table, My Tasks and the portfolio, long before the task is due to start.
7. Plans change, orders stay under control
If the number of units on a task changes, lines that are not ordered yet follow automatically. Ordered lines never change by themselves: procurement sees the requirement change and decides, and the project manager can send a change request with a note and a link. Every change in both products goes into the change log: who, when, what and why.
Reports, cost and cash management
Exepron Procurement has four reports: a vendor order list ready to send as PDF or Excel, the delivery schedule, late and at-risk lines to chase, and vendor performance with each vendor’s on-time deliveries and average delay.

In Exepron, material costs flow into the cost reports. The project cost summary and earned value include direct materials: planned from the needed quantity and price, actual from what was delivered.
The result: every task starts with its full kit
- Import and select your vendors and materials.
- Categorize the resource types, so materials stay out of leveling.
- Build the materials list once, put the requirement on each task, and the Full Kit list follows.
- Procurement orders and receives, and the project manager sees every part, every delay and every change on the task itself.
See it on your own projects
Exepron Procurement is available in the Exepron App Store for Exepron accounts. Want to see how it fits your projects? Contact us for a live demo, or start with Exepron for free.